FM 1187 I-20/I-30 Interchange Construction in Aledo: What's Open

A covered limestone entry with an oak front door, multi-pane window, timber beam and broad stone steps beside flowering sage.

TxDOT finished two pieces of the FM 1187 interchange this fall, and both help drivers coming home to Aledo. On Sept. 17, the westbound I-30 exit to FM 1187/FM 3325 was placed into permanent service. On the same day, the westbound I-20 frontage road approaching the intersection moved onto new pavement with a dedicated left-turn lane, a through lane, and a shared through-and-right lane. Going the other way, the eastbound I-30 entrance from FM 1187 is still closed. TxDOT's ramp notice puts that detour in effect "through Spring 2027 (weather permitting)."

The split is lopsided, and it decides which half of the day gets easier and which stays the same for roughly six more months. Here is the picture as of the first week of October 2026, movement by movement.

Why the Interchange Is Torn Up in the First Place

The work at FM 1187 is part of TxDOT's Keep 20-30 Moving program, three projects that together total $541 million. The piece that matters most to Aledo is Project 2. It covers I-20 and I-30 from FM 1187/FM 3325 to Linkcrest Drive. It includes ramp changes and auxiliary lanes to ease congestion between FM 1187 and the I-20/I-30 split. It also lowers the interstate mainlanes to make room under the bridges at FM 1187 and Walsh Ranch Parkway. Project 2 began in September 2024 and is scheduled to finish in early 2028.

Lowering the mainlanes under the bridges is why the ramps have moved around so much. Every ramp touching FM 1187 has to be rebuilt to meet a highway sitting at a different height. That means closing old ramps, opening temporary ones, and switching to permanent ones one at a time.

To the west, Project 1 covers I-20 from Markum Ranch Road to the I-20/I-30 split, including new interchanges at Bentley Drive and Walsh Ranch Parkway. TxDOT's project page still estimates completion in "early 2026." In March, the Fort Worth Report said Project 1 was expected to finish later this year. Neither TxDOT nor local news has published a notice that Project 1 is done, so treat those interchanges as still in progress.

The Westbound Side, Mostly Finished

Coming home from Fort Worth used to mean a string of temporary arrangements. Most of the permanent pieces on that side are now open.

In mid-March, TxDOT permanently closed the old westbound I-20 exit to FM 1187/FM 3325 so it could build a new westbound entrance ramp there. Westbound I-20 traffic now uses a permanent exit, still numbered Exit 420, located in the I-30 interchange area. TxDOT spokesperson Shawna Russell Jones told the Fort Worth Report the replacement exit would sit east of the closed ramp.

The Sept. 17 opening of the westbound I-30 exit to FM 1187/FM 3325 finished the other half. Drivers coming west on either interstate now have a permanent way off at Aledo. The westbound frontage road also moved to new pavement for what TxDOT calls "the final phase of construction" at the intersection.

There is one gain on the eastbound side too. On Aug. 21, the eastbound I-20 frontage road from FM 1187 returned to full service, and so did the northbound free right turn. If you leave Aledo heading north on FM 1187 and turn right onto the eastbound frontage road, that right turn no longer has to wait for the signal.

The Eastbound Side, Still on Detours

The morning trip toward Fort Worth carries most of the remaining 2027 dates.

Eastbound movement Status as of early October 2026 What drivers do now Expected return
I-30 entrance from FM 1187/FM 3325 Closed since March 19 so a permanent ramp can be built in its place Eastbound frontage road to the Walsh Ranch Parkway entrance Spring 2027, weather permitting
I-20 entrance from FM 1187/FM 3325 Moved to the new permanent ramp March 19 Enter about 1.25 miles east of the old ramp Permanent now
I-30 exit to Walsh Ranch Parkway Returned to service Aug. 14 Normal use Done
I-30 exit to Spur 580 Closed Aug. 14 for reconstruction Eastbound I-20 to northbound FM 2871 Winter 2027
I-30 exit to Alemeda Street Closed Aug. 14 for reconstruction Exit at Chapel Creek Boulevard and continue on the eastbound frontage road Spring 2027
I-30 entrance from Spur 580 Closed Aug. 14 for reconstruction Eastbound Spur 580 to northbound I-820 Spring 2027

From Aledo, getting onto eastbound I-30 still means taking the frontage road to Walsh Ranch Parkway. Leaving I-30 eastbound before Loop 820 has gotten harder as well. Since Aug. 14, the Spur 580 and Alemeda Street exits have both been closed, and each sends drivers on its own detour. If your morning ends near Camp Bowie West or Alemeda, those closures matter more than anything happening at FM 1187.

The westbound side has one exception. On Sept. 25, TxDOT closed the westbound I-30 frontage road from RM 2871 to the westbound exit to Chapel Creek Boulevard for reconstruction, with a return expected in winter 2027. The detour runs north on Academy Boulevard, then west on Amber Ridge Drive. On the same day, the RM 2871/Longvue Avenue bridge over I-30 came back into service. Access south from the bridge to Spur 580 is still closed.

What Stays Narrow Regardless of Direction

The ramp openings did not add lanes. I-20 is still down to two travel lanes in each direction between the I-20/I-30 split and FM 1187/FM 3325. TxDOT lists the reduction as "ongoing" and gives no end date. I-30 is also down to two lanes each way between Linkcrest Drive and West Loop 820, also with no posted end date. When the program is finished, the roadway will go from two general-purpose lanes in each direction to three. The two narrowed stretches belong to different projects with different dates. The I-20 section near FM 1187 falls within Project 2, scheduled for early 2028. The I-30 section from Linkcrest Drive to West Loop 820 is Project 3, which TxDOT estimates will be finished in 2030.

The backups at the interchange have made the local news. On Aug. 13, The Community News ran a photo of traffic stacked up on the I-20 service road approaching the FM 1187/FM 3325 intersection. The same story described a push for coordination by Aledo Mayor Shane Davis. He met with Jones on Aug. 4. Later that day he met with representatives of Aledo ISD, the City of Willow Park, TxDOT, Parker County, Parker County ESD, the City of Fort Worth, and the City of Aledo to go over current projects, timelines, and likely problems.

"There's so many projects going on, and no one [was] talking to each other, and so we just needed to get everybody in one room…to make sure that we could come up with an organized plan so the greater community could travel, get to school, and we could communicate together as one, rather than separate entities." Aledo Mayor Shane Davis, to The Community News

Davis said Jones is a Parker County resident and has been assigned to work with the city so updates arrive faster. He said he would pass updates along to the community and asked her to share information with Willow Park and Fort Worth as well. His advice to drivers was plain. Leave a little earlier than usual, obey the speed limit, and watch for changing conditions. He also said law enforcement would be more visible once school started.

October Closures Around FM 1187

TxDOT generally schedules weekday closures from 9 a.m. to 3 p.m. and weeknight closures from 7 p.m. to 6 a.m. Lane closures are allowed all day Saturday and on Sunday as needed. Every listing can change with weather or schedule. These are the closures posted for the next two weeks closest to Aledo:

  1. Daily, Oct. 5–10, 9 a.m.–3 p.m.: The right turn bay from northbound FM 1187 to the eastbound I-20 frontage road is closed. That's the same turn that reopened in August.
  2. Daily, Oct. 5–10, 9 a.m.–3 p.m.: The outside lane of the eastbound I-20 frontage road is closed for half a mile east of FM 1187. Shoulders on I-20 between FM 1187 and the I-20/I-30 interchange are also closed.
  3. Nightly, Oct. 7–10, 7 p.m.–6 a.m.: I-20 drops to one lane in each direction at the FM 1187/FM 3325 underpass for utility work. TxDOT warns drivers to expect delays.
  4. Oct. 15 at 7 p.m. through Oct. 20 at 6 a.m.: The westbound I-30 entrance from Chapel Creek Boulevard is closed. Traffic is sent south to Spur 580, then west under I-30 to the entrance ramp east of Linkcrest Drive.
  5. Friday, Oct. 16 at 7 p.m. through Monday, Oct. 19 at 6 a.m.: The outside lane of northbound FM 1187 crossing I-20 is closed around the clock for bridge repair.

The weekend of Oct. 16–19 is the one to plan around. For three nights and two full days, northbound FM 1187 will have one fewer lane over I-20. The first item on the list also closes the right turn bay the August reopening restored, during weekday daytime hours this week.

South of the Interstate, FM 1187 Is Still on Paper

The other big project on Aledo's main road is still in design. Parker County's widening of FM 1187 from FM 5 to Aledo-Iona Road shows 40% overall progress on the county bond program's project page. It lists continued coordination with TxDOT and the North Central Texas Council of Governments, and no completion date. The Community News covered the county commissioners' transportation update on Sept. 17. That coverage also has no construction start date for the widening.

At the interchange, the dates that matter most for Aledo drivers are spring 2027 for the eastbound I-30 entrance, winter and spring 2027 for the I-30 ramps at Spur 580 and Alemeda Street, early 2028 for Project 2, and 2030 for the Project 3 stretch of I-30 east of Linkcrest Drive. TxDOT updates its live roadwork page at txdot.gov/keep20-30moving as closures change.

If you're timing a home sale or purchase around Aledo's I-20/I-30 schedule, or you just want to know how the 2027 ramp dates affect daily life near FM 1187, talk with the local Springtown team at Lori Mayo Real Estate Group. We follow these east Parker County corridors closely and are happy to walk you through them.